Barrenjoey High School
During 22 weeks of construction, 6,040m2 of metal roof sheets were laid and 1,293m2 of cladding installed across six school buildings.
The scope of works included:
- Installation of seven new whirly bird ventilators
- Installation of six new dome skylights to the library
- Installation of ten new skylights to the sports hall
- Replacement of fascias, purlins, wire, insulation and roof ventilators
All works were completed within a live school environment with careful planning to minimise the impact of students during their exams.
Sector
Education, Roofing
Value
$1.76 million
Client
Department of Education (DoE)
Duration
November 2017 - April 2018